Sea-Bird Electronics SBE 38 Dokumentacja Strona 251

  • Pobierz
  • Dodaj do moich podręczników
  • Drukuj
Przeglądanie stron 250
1/16/2012
19
First Cast of the Day
W
et the conductivity cell in accordance with
Application Note 2D, approximately 1 hour before
the cast.
Before taking the first cast:
Verify all cables and dummy plugs are installed.
Verify all plumbing is properly connected.
Remember to remove the soaker tube from the conductivity
cell, covers from PAR sensors, pH bottles, etc.
Making a checklist that includes all sensors in your
configuration
can help prevent things from being overlooked.
Page 251 of 258
Przeglądanie stron 250

Komentarze do niniejszej Instrukcji

Brak uwag